The Boeing 787, All Nippon Airways ZA511 Production Flight Test Progress Summary

The All Nippon Airways ZA511 Production Flight Test Summary includes all flights completed up to and including those up to the day af delivery, October 31st, 2012. The last production test flight occurred October 28th, 2012.

Flights Completed on ZA511: 5; Time Flown: 5.75 hours

Maximum Altitude Achieved: 39,000 feet; Maximum Mach Number: .93

Production Flight Test Duration: 16; Days Flown: 3; Flights Flown: 5; Days From First Flight to Delivery: 19

Note: Flights completed includes landings to a full stop. Touch and go's and take off and landing performance flight with multiple landings are not reflected in the data given here. The number of missions can be lower than the reported number of flights. A flight mission can include any number of landings. Gaps in tracking data exist, lowering the flight hours shown here when compaired to the actual flight time recorded during flight testing. Since the data presented here is from public sources, FAA Radar Tracking Data, data gaps are normal occurances and do not reflect on the flight test program. Radar tracking data is only available when a flight plan has been filed and it is active. If a flight plan has been canceled in flight, the tracking ends and data is no longer available.

On September 24th 2011, the first All Nippon Airways Boeing 787 was delivered. Fifty two airplanes were ordered, 22 787-8's and 30 787-9's. ZA511 was the 16th 787-8 delivered. The information presented below is an unofficial summary of the ZA511 production flight test program status. The information presented here is from publicly available data and is presented only for informative purposes. Additional information and data for other test aircraft will be presented once it becomes available.

All Nippon Airways 787 ZA511 Flight Test Progress